TY - JOUR A1 - Likhitruangsilp, Veerasak A1 - Ioannou, Photios T1 - Risk-sensitive Markov Decision Process for Underground Construction Planning and Estimating N2 - This paper presents an application of dynamic decision making under uncertainty in planning and estimating underground construction. The application of the proposed methodology is illustrated by its application to an actual tunneling project—The Hanging Lake Tunnel Project in Colorado, USA. To encompass the typical risks in underground construction, tunneling decisions are structured as a risk-sensitive Markov decision process that reflects the decision process faced by a contractor in each tunneling round. This decision process consists of five basic components: (1) decision stages (locations), (2) system states (ground classes and tunneling methods), (3) alternatives (tunneling methods), (4) ground class transition probabilities, and (5) tunneling cost structure. The paper also presents concepts related to risk preference that are necessary to model the contractor’s risk attitude, including the lottery concept, utility theory, and the delta property. The optimality equation is formulated, the model components are defined, and the model is solved by stochastic dynamic programming. The main results are the optimal construction plans and risk-adjusted project costs, both of which reflect the dynamics of subsurface construction, the uncertainty about geologic variability as a function of available information, and the contractor’s risk preference. KW - Mehragentensystem KW - Lernendes System KW - Tunnel KW - Markowschke KW - Kette Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2247 ER - TY - JOUR A1 - Yabuki, Nobuyoshi A1 - Kotani, Jun A1 - Shitani, Tomoaki T1 - A Steel Bridge Design System Architecture using VR-CAD and Web Service-based Multi-Agents N2 - This paper presents a new design environment based on Multi-Agents and Virtual Reality (VR). In this research, a design system with a virtual reality function was developed. The virtual world was realized by using GL4Java, liquid crystal shutter glasses, sensor systems, etc. And the Multi-Agent CAD system with product models, which had been developed before, was integrated with the VR design system. A prototype system was developed for highway steel plate girder bridges, and was applied to a design problem. The application verified the effectiveness of the developed system. KW - Mehragentensystem KW - Lernendes System KW - Stahlbrücke KW - Virtuelle Realität Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2146 ER - TY - JOUR A1 - Wehner, R. A1 - Steinmann, Frank A1 - Hübler, Reinhard T1 - FLEXOB - Entwicklungstool für dynamische, modellbasierte CAD-Systeme N2 - Objektorientierte Modellierungstechniken werden gegenwärtig vor allem Entwicklern von CAD-Systemen angeboten. Sie erzeugen über die Schritte OO-Modellanalyse und OO-Softwaredesign OO-Programme, die mit ihrer Compilation das durch den Softwareingenieur gefundene Modell festschreiben. Generell, aber insbesondere im Bauwerksdesign, ist dieses Vorgehen unbefriedigend, da hier eine Normung von Modellen nicht gelingt, der Entwurfsprozeß vergleichsweise lang ist und eine Kooperation von Ingenieurgewerken mit verschiedenen Modelldomänen die Regel sind. Darüber hinaus weisen die Modelle in frühen Phasen ein hohes Maß an Unschärfe und Abstraktion auf. CAD-Tools, die diese Phasen unterstützen, benötigen deshalb: statt eines genormten Produktmodells ein einheitliches, kognitiv begründetes Modellstrukturierungsparadigma, für das mit der Objektorientierung eine mögliche Ausprägung gegeben ist, ein explizites, verfügbares Domänenmodell zur fortwährenden Interpretation von Bauwerksmodellen, deskriptive Elemente, die die Interpretation von Objekten und Attributen erleichtern, ein Konzept zur Behandlung von Unschärfe und Abstraktion. Hieraus ergeben sich für die Entwicklung von CAD-Systemen folgende Forderungen : Explizite Verfügbarkeit von Klassenobjekten und deren Erzeugung und Veränderung zur Laufzeit, Vererbung auf Klassen- und Instanzniveau, Erweiterte Attributkonzepte (Facetten), Unterstützung der Aggregation als einer wesentlichen Modellstrukturierungsrelation, Verfügbarkeit von OO-Schnittstellen zum Aufbau von CAD-Systemen aus Tools einerseits, sowie zur Trennung von Modellverwaltung und Modellrepräsentation andererseits. Als ein herausragendes Merkmal des Objektorientierten Paradigmas wird die Anwendungsnähe genannt, da Erscheinungen der behandelten Domäne sich analog in Modellen und Programmen wiederfinden (sollen). Unter der Grundannahme, daß dieses Paradigma auch durch den Anwender zur Erstellung seiner Modellwelten verwendet wird, will FLEXOB eine homogene Umgebung schaffen, die die Modellwelt des Softwareingenieurs zu Analysezwecken dem Anwender zur Verfügung stellt und die die Erweiterung dieser Modellwelt auf deskriptivem Niveau ermöglicht. Das Tool FLEXOB und einige wesentliche Implementationsdetails werden im Beitrag vorgestellt. Es handelt sich bei diesem Tools um eine C++ Klassenbibliothek, die entweder als Objektmodul oder als Windows-DLL verwendet werden kann. Aspekte des Nutzungsregimes solch flexibler Modellverwaltungen werden im Beitrag ebenfalls angespochen. KW - CAD KW - Modellierung Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-4571 ER - TY - JOUR A1 - van Treeck, Christoph A1 - Rank, Ernst T1 - Analysis of building structure and topology based on Graph Theory N2 - Individual views on a building product of people involved in the design process imply different models for planning and calculation. In order to interpret these geometrical, topological and semantical data of a building model we identify a structural component graph, a graph of room faces, a room graph and a relational object graph as aids and we explain algorithms to derive these relations. The application of the technique presented is demonstrated by the analysis and discretization of a sample model in the scope of building energy simulation. KW - Produktmodell KW - Simulation KW - Bautechnik KW - Graphentheorie KW - Ingenieurbau Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2308 ER - TY - JOUR A1 - Lizounov, P. P. T1 - Dynamics of solid and deformable Bodies Systems at complex Movements N2 - Analytical models, describing oscillations of systems of interconnected solid and deformable bodies,making a complex movement in fields of inertia forces and gravitation forces, are resulted. Method of numerical investigation of dynamics of the specified systems, based on sharing of parameter prolongation method, Newton-Kantorovich algorithm, Flocke and Liapunov hteories, is developed. On the basis of constructed analytical models and numerical techniques a new, practically important problems of dynamics of systems, consisting of solid bodies, flexible rods, membranes and soft shells, which make a complex movement in fields of forces of inertia and gravity are solved. The received results are used during designing of responsible elements of structures, making a complex movement, which find application in construction and mechanical engineering. KW - Festkörpermechanik KW - Dynamische Belastung KW - Numerisches Verfahren Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-5410 ER - TY - JOUR A1 - Weise, Matthias A1 - Katranuschkov, Peter A1 - Scherer, Raimar J. T1 - Generic Services for the Support of Evolving Building Model Data N2 - Many problems related to data integration in AEC can be better tackled by an approach that takes into account the heterogeneity of tasks, models and applications but does not require continuous consistency of the evolving design data, at each data management operation. Such an approach must incorporate adequate services that can facilitate reintegration of concurrently modified data at reasonably selected coordination points. In this paper we present a set of methods which, used in combination, can achieve that goal. After a description of the principal envisaged cooperative work scenario each of these methods is discussed in detail and current observations drawn from their software realisation are given. Whilst the suggested approach is valid for any EXPRESS-based data model, the practical focus of work has been on facilitating IFC-driven integration. KW - Produktmodell KW - Bautechnik KW - Forschungskooperation KW - EXPRESS Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2077 ER - TY - JOUR A1 - Abdalla, Jamal T1 - Elements of an Agent-based Mediative Communication Protocol for Design Objects N2 - Integrated structural engineering system usually consists of large number of design objects that may be distributed across different platforms. These design objects need to communicate data and information among each other. For efficient communication among design objects a common communication protocol need to be defined. This paper presents the elements of a communication protocol that uses a mediator agent to facilitate communication among design objects. This protocol is termed the Mediative Communication Protocol (MCP). The protocol uses certain design communication performatives and the semantics of an Agent Communication language (ACL) mainly the Knowledge and Query Manipulation Language (KQML) to implement its steps. Details of a Mediator Agent, that will facilitate the communication among design objects, is presented. The Unified Modeling Language (UML) is used to present the Meditative protocol and show how the mediator agent can be use to execute the steps of the meditative communication protocol. An example from structural engineering application is presented to demonstrate and validate the protocol. It is concluded that the meditative protocol is a viable protocol to facilitate object-to-object communication and also has potential to facilitate communication among the different project participants at the higher level of integrated structural engineering systems. KW - Mehragentensystem KW - Lernendes System KW - Kommunikationsprotokoll Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2207 ER - TY - JOUR A1 - Gao, Zuoren A1 - Wu, Weiyu A1 - Ren, Aizhu T1 - Physically Based Modeling and Multi-Physical Simulation System for Wood Structure Fire Performance N2 - This research is devoted to promoting the performance-based engineering in wood structure fire. It looks into the characteristic of the material, structural composing and collapse detecting to find out the main factors in the wood structure collapse in fire. The aim of the research is to provide an automatic simulation platform for the complicated circulation. A physically based model for slim member for beams and columns and a frame of multi-physical simulation are provided to implement the system. The physically based model contains material model, structural mechanics model, material mechanics model, as well as geometry model for the compositive simulation. The multi-physical simulation is built on the model and has the capacity to carry out a simulation combining structural, fire (thermal, CFD) and material degradation simulation. The structural and fire simulation rely on two sophisticated software respectively, ANSYS (an FEA software) and FDS (with a core of CFD). Researchers of the paper develop system by themselves to combine the two existing ones. The system has the capability to calculate the wood char to find out the loss of cross-section and to detect the collapse caused in different ways. The paper gives a sample of Chinese traditional house to show how this simulation system works. KW - Produktmodell KW - Simulation KW - Bautechnik KW - Holzbau KW - Brandschutz Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2381 ER - TY - JOUR A1 - Takagi, Kousuke A1 - Tani, Akinori A1 - Kawamura, Hiroshi T1 - Research on Intelligent Fuzzy Optimal Active and Hybrid Control Systems of Building Structures - Verification of Optimization Method on Switching Rules of Control Forces N2 - Recently, many reseraches on active control systems of building structures are preformed based on modern control theory and are installed real buildings. The authors have already proposed intelligent fuzzy optimal active control (IFOAC) systems. IFOAC systems imitate intelligent activities of human brains such as prediction, adaptation, decision-kaking and so on. In IFOAC systems, objective and subjective judgements on the active control can be taken into account. However, IFOAC systems are considered to be suitable for far-field erathquake and control effect becomes small in case of near-field earthqaukes which include a few velosity pules with large amplitudes. To improve control effect in case of near-souece earthquakes, the authors have also proposed hybrid control (HC) systems, in which IFOAC systems and fuzzy control system are combined. In HC systems, the fuzzy control systems are introduced as a reflective fuzzy active control (RFAC) system and imitates spinal reflection of human. In HC systems, active control forces are activated to buildings in accordance with switching rules on active control forces. In this paper, optimizations on fuzzy control rules in RFAC system and switching rules of active control forces in HC system are performed by Parameter-Free Genetic Algorithms (PfGAs). Here, the optimization is performed by using different earthquake inputs. The results of digital simulations show that the HC system can reduce maximal response displacements under restrictions on strokes of the actuator effectively in case of a near-source earthquake and the effectiveness of the proposed HC system is discussed and clarified. KW - Mehragentensystem KW - Lernendes System KW - Fuzzy-Logik KW - Optimierung Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2238 ER - TY - JOUR A1 - Willenbacher, Heiko A1 - Hübler, Reinhard T1 - Intelligent Link-Management for the Support of Integration in Building Life Cycle N2 - The processes in the life cycle of buildings are characterised by highly distinct teamwork. The integration of all the distributed working participants, by providing an environment, which especially supports the communication and collaboration between the actors, is a fundamental step to improve the efficiency of the involved processes and to reduce the total costs. In this article, a link based modelling approach and its “intelligent” link management is introduced (1). This approach realises an integration environment based on a special building model that acts as a decision support system. The link-based modelling is characterised by the definition and specialisation of links between partial models. These intelligent managed links enable a very flexible and task specific data access and exchange between all the different views and partial models of the participants. KW - Mehragentensystem KW - Lernendes System KW - Bauwerk KW - Lebenszyklus Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2223 ER - TY - JOUR A1 - Motawa, Ibrahim A1 - Anumba, Chimay A1 - El-Hamalawi, A. T1 - Development of a Fuzzy System for Change Prediction in Construction Projects N2 - Change management has been the focus of different IT systems. These IT systems were developed to represent design information, record design rationale, facilitate design coordination and changes. They are largely based on managing reactive changes, particularly design changes, in which changes are recorded and then propagated to the relevant project members. However, proactive changes are hardly dealt with in IT systems. Proactive changes require estimating the likelihood of occurrence of a change event as well as estimating the degree of change impacts on project parameters. Changes in construction projects often result from the uncertainty associated with the imprecise and vague knowledge of much project information at the early stages of projects. This is a major outcome of the case studies carried out as part of this research. Therefore, the proposed model considers that incomplete knowledge and certain project characteristics are always behind change causes. For proactive changes, predicting a change event is the main task for modelling. The prediction model should strive to integrate these main elements: 1) project characteristics that lead to change 2) causes of change, 3) the likelihood of change occurrence, and 4) the change consequences. It should also define the dependency relationships between these elements. However, limited data (documented) are only available from previous projects for change cases and many of the above elements can only be expressed in linguistic terms. This means that the model will simulate the uncertainty and subjectivity associated with these sets of elements. Therefore, a fuzzy model is proposed in this research to capture these elements. The model analyses the impact of each set of elements on the other by assigning fuzzy values for these elements that express the uncertainty and subjectivity of their impact. The main aim is to predict change events and evaluate change effects on project parameters. The fuzzy model described above was developed in an IT system for operational purposes and was designed as a Java package of components with their supporting classes, beans, and files. This paper describes the development and the architecture of the proposed IT system to achieve these requirements. The system is intended to help project teams in dealing with change causes and then the change consequences in construction projects. KW - Mehragentensystem KW - Lernendes System KW - Fuzzy-Logik Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2180 ER - TY - JOUR A1 - Foorgber, U. A1 - Müller, Christian T1 - A Planning Process Model for Computer Supported Cooperative Work in Building Construction N2 - Increasing complexity of today's buildings requires a high level of integration in the planning process. Common planning strategies, where individual project partners cooperate mainly to exchange results, are not suitable to jointly develop project goals and objectives. Integrated planning, a more holistic approach to deal with complex problems, is based on a high degree of communication amoung team members and leads to a goal oriented cooperation. Current approaches in the reasearch area of Computer Supported Cooperative Work (CSCW) poorly meet the requirements in planning. A planning process model, based on the principles of integrated planning will be introduced, aimed to provide the background for the implementation of a CSCW-platform. KW - Bauwesen KW - Integrierte Planung KW - Computer Supported Cooperative Work Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-4922 ER - TY - JOUR A1 - Yabuki, Nobuyoshi A1 - Yoshimura, Yutaka T1 - An Evaluation System for Steel Structures of Hydroelectric Power Stations based on Fault Tree Analysis and Performance Maps N2 - This paper presents an evaluation system for steel structures of hydroelectric power stations, including hydraulic gates and penstocks, based on Fault Tree Analyasis (FTA) and performance maps. This system consists of fault tree diagrams of FTA, performance maps, design and analysis systems, and engineerin databases. These four modules are integrated by appropriate hyperlinks so that the user of this system can use it easily and seamlessly. A well developed system was applied to some illustrative example cases, and they showed that the developed methodology and system worked well and the users found the system useful and effective for their maintenance tasks at powerstations. KW - Wissensmanagement KW - Stahlbau KW - Wasserkraftwerk Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2564 ER - TY - JOUR A1 - Kicinger, Rafal A1 - Arciszewski, Tomasz A1 - De Jong, Kenneth T1 - Distributed Evolutionary Design: Island-Model-based Optimization of Steel Skeleton Structures in Tall Buildings N2 - This paper presents results of a study on distributed, or parallel, evolutionary computation in the topological design of steel structural systems in tall buildings. It describes results of extensive experimental research on various parallel evolutionary architectures applied to a complex structural design problem. The experiments were conducted using Inventor 2003, a networkbased evolutionary design support tool developed at George Mason University. First, a general introduction to evolutionary computation is provided with an emphasis on recent developments in parallel evolutionary architectures. Next, a discussion of conceptual design of steel structural systems in tall buildings is presented. Further, Inventor 2003 is briefly introduced as well as its design representation and evolutionary computation characteristics. Next, the results obtained from systematic design experiments conducted with Inventor 2003 are discussed. The objective of these experiments was to qualitatively and quantitatively investigate evolution of steel structural systems in tall buildings during a distributed evolutionary design process as well as to compare efficiency and effectiveness of various parallel evolutionary architectures with the traditional evolutionary design approaches. Two connectivity topologies (ring topology and fully-connected topology) have been investigated for four populations of structural designs evolving in parallel and using various migration strategies. Also, results of the initial sensitivity studies are reported in which two ways of initializing distributed evolutionary design processes were investigated, using either arbitrarily selected designs as initial parents or randomly generated ones. Finally, initial research conclusions are presented. KW - Mehragentensystem KW - Lernendes System KW - Stahlbau KW - Skelettbau KW - Optimierung Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2195 ER - TY - JOUR A1 - Milbradt, Peter A1 - Schierbaum, Jochen A1 - Schwöppe, Axel T1 - Finite Cell-Elements of Higher Order N2 - The method of the finite elements is an adaptable numerical procedure for interpolation as well as for the numerical approximation of solutions of partial differential equations. The basis of these procedure is the formulation of suitable finite elements and element decompositions of the solution space. Classical finite elements are based on triangles or quadrangles in the two-dimensional space and tetrahedron or hexahedron in the threedimensional space. The use of arbitrary-dimensional convex and non-convex polyhedrons as the geometrical basis of finite elements increases the flexibility of generating finite element decompositions substantially and is sometimes the only way to get a clear decomposition... KW - Finite-Elemente-Methode KW - Physikalisches Verfahren Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2524 ER - TY - JOUR A1 - El-Rayes, Khaled A1 - Hyari, Khalied T1 - A Multi-objective Model for Optimizing Construction Planning of Repetitive Infrastructure Projects N2 - This paper presents the development of a model for optimizing resource utilization in repetitive infrastructure projects. The model provides the capability of simultaneous minimization of both project duration and work interruptions for construction crews. The model provides in a single run, a set of nondominated solutions that represent the tradeoff between these two objectives. The model incorporates a multiobjective genetic algorithm and scheduling algorithm. The model initially generates a randomly selected set of solutions that evolves to a near optimal set of tradeoff solutions in subsequent generations. Each solution represents a unique scheduling solution that is associated with certain project duration and a number of interruption days for utilized construction crews. As such, the model provides project planners with alternative schedules along with their expected duration and resource utilization efficiency. KW - Mehragentensystem KW - Lernendes System KW - Infrastruktur Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2135 ER - TY - JOUR A1 - Rüppel, Uwe T1 - Multimediale Gestaltung von Bestandsverwaltungsprozessen im Bauwesen N2 - Die Kosten für die Unterhaltung von Bauwerken über den Lebenszyklus sind im Vergleich zu den Planungs- und Herstellungskosten erheblich größer. Insbesondere setzt eine Reduzierung des Instandhaltungsaufwandes als Teilprozeß der Bestandsverwaltung das rechtzeitige Erkennen von Bauschäden und das vorausschauende Ergreifen von Gegenmaßnahmen voraus. Das planmäßige Vorgehen beim Erkennen von Bauschäden, d.h. die regelmäßige Überwachung baulicher Anlagen, dient nicht nur dem sparsamen Umgang mit vorhandenen Mitteln, sondern verringert auch die Gefahr des plötzlichen Versagens von tragenden Bauteilen. Dadurch werden Gefahren für die Nutzer der Bauwerke frühzeitig abgewendet. Die Notwendigkeit der systematischen Instandhaltung mit modernen Methoden wird auch in den Schlußfolgerungen des dritten Bauschadensberichts des Bundesministeriums für Raumordnung, Bauwesen und Städtebau unterstrichen. Um den Zustand eines Bauteils festzustellen, werden ausreichende Informationen über Struktur, Material, Alter, Belastungen, Umweltbedingungen etc. benötigt. Zur Verarbeitung dieser Fülle von Informationen unterschiedlichen Typs (z.B. technische Dokumente, CAD-Zeichnungen, Photos etc.) bei der Überwachung und Dokumentation baulicher Anlagen ist eine geeignete DV-Unterstützung notwendig. Zur Verwaltung der komplexen Baustrukturinformationen werden objektorientierte Bauwerksmodelle benötigt. Zur bedarfsgerechten Aufbereitung der unterschiedlichen Informationsarten und -qualitäten ist zusätzlich eine multimediale Informationsverarbeitung sowohl intern als auch in der Benutzungsschnittstelle erforderlich. Im Beitrag werden die Grundlagen objektorientierter Methoden zur Bauwerksmodellierung sowie von Multimedia mit den Bereichen Text, Graphik (Vektor- und Pixelgraphik), Audio, Photo und Video einschließlich deren Verknüpfungsmöglichkeiten im Sinne von Hypermedia an Beispielen erläutert. Zusätzlich werden aktuelle Entwicklungstendenzen im Bereich der Telekommunikation mit den Möglichkeiten des Computernetzes INTERNET zur Bestandsverwaltung in verteilten Systemen aufgezeigt. Abschließend werden Anwendungen der objektorientierten und multimedialen Informationsverarbeitung in der täglichen Ingenieurpraxis am Beispiel des DV-Systems BestandManager zur Überwachung und Dokumentation baulicher Anlagen vorgestellt. KW - Bauwerk KW - Langzeitverhalten KW - Bauschaden KW - Instandhaltung KW - Objektmodell Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-4839 ER - TY - JOUR A1 - Kaklauskas, Gintaris A1 - Cervenka, Vladimir A1 - Cervenka, Jan T1 - Deflection Calculation of RC Beams: Finite Element Software versus Design Code Methods N2 - The paper investigates accuracy of deflection predictions made by the finite element package ATENA and design code methods ACI and EC2. Deflections have been calculated for a large number of experimental reinforced concrete beams reported by three investigators. Statistical parameters have been established for each of the technique at different load levels, separately for the beams with small and moderate reinforcement ratio. KW - Finite-Elemente-Methode KW - Physikalisches Verfahren KW - Balken Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2498 ER - TY - JOUR A1 - Minch, M. J. A1 - Trochanowski, A. T1 - The numerical Modelling and Analysis of RC cracked Structures N2 - The purpose of this paper is to review model for finite element techniques for non-linear crack analysis of reinforced concrete beams and slabs. The non-linear behaviour of concrete and steel were described. Some calculations of >self-stress< for concrete and reinforced concrete beam was made. Current computational aspects are discussed. Several remarks for future studies are also given. The numerical model of the concrete and reinforced concrete was described. The paper shows the results of calculations on a reinforced concrete plane stress panel with cracks. The non-linear, numerical model of calculations of reinforced concrete was assumed. Using finite elements method some calculations were made. The results of calculations like displacements, stresses and cracking are shown on diagrams. They were compared with experimental results and other finding. Some conclusions about the described model and results of calculation are shown. KW - Tragwerk KW - Stahlbeton KW - Rissbildung KW - Modellierung Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-5278 ER - TY - JOUR A1 - Dudek, Mariusz T1 - Zur Bewertung der Struktur von Verkehrsnetzen N2 - In diese Veröffentlichung werden die Kennziffern dargestellt, die zur Beurteilung der Struktur von Verkehrsnetzen behilflich sein können. Zu diesem Zweck wurde die Graphentheorie angewendet. Eine erste Gruppe von Bewertungen stützt sich auf die Anzahl der Knoten und Bögen des Netzes. Detailliertere Informationen über Engpässe oder Schwachstellen im Verkehrsnetz erhält man durch die Analyse der Kantenzusammenhangs. Die Unabhängigkeit der einzelnen Verkehrsarten , ihre Bewertung und Maßnahmen, sie zu verbessern werden vorgeschlagen und diskutiert. Weiteren Untersuchungen werden angeregt. KW - Verkehrsnetz KW - Kennzahl KW - Bewertung KW - Graphentheorie Y1 - 1997 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-4634 ER -