TY - CHAP A1 - Ignatova, Elena A1 - Kirschke, Heiko A1 - Tauscher, Eike A1 - Smarsly, Kay ED - Gürlebeck, Klaus ED - Lahmer, Tom T1 - PARAMETRIC GEOMETRIC MODELING IN CONSTRUCTION PLANNING USING INDUSTRY FOUNDATION CLASSES T2 - Digital Proceedings, International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering : July 20 - 22 2015, Bauhaus-University Weimar N2 - One of the most promising and recent advances in computer-based planning is the transition from classical geometric modeling to building information modeling (BIM). Building information models support the representation, storage, and exchange of various information relevant to construction planning. This information can be used for describing, e.g., geometric/physical properties or costs of a building, for creating construction schedules, or for representing other characteristics of construction projects. Based on this information, plans and specifications as well as reports and presentations of a planned building can be created automatically. A fundamental principle of BIM is object parameterization, which allows specifying geometrical, numerical, algebraic and associative dependencies between objects contained in a building information model. In this paper, existing challenges of parametric modeling using the Industry Foundation Classes (IFC) as a federated model for integrated planning are shown, and open research questions are discussed. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Building Information Modeling KW - Computerunterstütztes Verfahren KW - Data, information and knowledge modeling in civil engineering; Function theoretic methods and PDE in engineering sciences; Mathematical methods for (robotics and) computer vision; Numerical modeling in engineering; Optimization in engineering applications Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28024 SN - 1611-4086 ER - TY - CHAP A1 - Smarsly, Kay A1 - Tauscher, Eike ED - Gürlebeck, Klaus ED - Lahmer, Tom T1 - IFC-BASED MONITORING INFORMATION MODELING FOR DATA MANAGEMENT IN STRUCTURAL HEALTH MONITORING T2 - Digital Proceedings, International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering : July 20 - 22 2015, Bauhaus-University Weimar N2 - This conceptual paper discusses opportunities and challenges towards the digital representation of structural health monitoring systems using the Industry Foundation Classes (IFC) standard. State-of-the-art sensor nodes, collecting structural and environmental data from civil infrastructure systems, are capable of processing and analyzing the data sets directly on-board the nodes. Structural health monitoring (SHM) based on sensor nodes that possess so called “on-chip intelligence” is, in this study, referred to as “intelligent SHM”, and the infrastructure system being equipped with an intelligent SHM system is referred to as “intelligent infrastructure”. Although intelligent SHM will continue to grow, it is not possible, on a well-defined formalism, to digitally represent information about sensors, about the overall SHM system, and about the monitoring strategies being implemented (“monitoring-related information”). Based on a review of available SHM regulations and guidelines as well as existing sensor models and sensor modeling languages, this conceptual paper investigates how to digitally represent monitoring-related information in a semantic model. With the Industry Foundation Classes, there exists an open standard for the digital representation of building information; however, it is not possible to represent monitoring-related information using the IFC object model. This paper proposes a conceptual approach for extending the current IFC object model in order to include monitoring-related information. Taking civil infrastructure systems as an illustrative example, it becomes possible to adequately represent, process, and exchange monitoring-related information throughout the whole life cycle of civil infrastructure systems, which is referred to as monitoring information modeling (MIM). However, since this paper is conceptual, additional research efforts are required to further investigate, implement, and validate the proposed concepts and methods. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Building Information Modeling KW - Computerunterstütztes Verfahren KW - Data, information and knowledge modeling in civil engineering; Function theoretic methods and PDE in engineering sciences; Mathematical methods for (robotics and) computer vision; Numerical modeling in engineering; Optimization in engineering applications Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28237 SN - 1611-4086 ER - TY - THES A1 - Richter, Torsten T1 - Konzepte für den Einsatz versionierter Objektmodelle im Bauwesen T1 - Concepts for the application of versioned object models in the building industry N2 - Bauwerke sind in der Regel Unikate, für die meist eine komplette und aufwändige Neuplanung durchzuführen ist. Der Umfang und die Verschiedenartigkeit der einzelnen Planungsaufgaben bedingen ein paralleles Arbeiten der beteiligten Fachplaner. Darüber hinaus ist die Bauplanung ein kreativer und iterativer Prozess, der durch häufige Änderungen des Planungsmaterials und Abstimmungen zwischen den Fachplanern gekennzeichnet ist. Mithilfe von speziellen Fachanwendungen erstellen die Planungsbeteiligten verschiedene Datenmodelle, zwischen denen fachliche Abhängigkeiten bestehen. Ziel der Arbeit ist es, die Konsistenz der einzelnen Fachmodelle eines Bauwerks sicherzustellen, indem Abhängigkeiten auf Basis von Objektversionen definiert werden. Voraussetzung dafür ist, dass die Fachanwendungen nach dem etablierten Paradigma der objektorientierten Programmierung entwickelt wurden. Das sequentielle und parallele Arbeiten mehrerer Fachplaner wird auf Basis eines optimistischen Zugriffsmodells unterstützt, das ohne Schreibsperren auskommt. Weiterhin wird die Historie des Planungsmaterials gespeichert und die Definition von rechtsverbindlichen Freigabeständen ermöglicht. Als Vorbild für die Systemarchitektur diente das Softwarekonfigurationsmanagement, dessen Versionierungsansatz meist auf einem Client-Server-Modell beruht. Die formale Beschreibung des verwendeten Ansatzes wird über die Mengenlehre und Relationenalgebra vorgenommen, so dass er allgemeingültig und technologieunabhängig ist. Auf Grundlage dieses Ansatzes werden Konzepte für den Einsatz versionierter Objektmodelle im Bauwesen erarbeitet und mit einer Pilotimplementierung basierend auf einer Open-Source-Ingenieurplattform an einem praxisnahen Szenario verifiziert. Beim Entwurf der Konzepte wird besonderer Wert auf die Handhabbarkeit der Umsetzung gelegt. Das betrifft im Besonderen die hierarchische Strukturierung des Projektmaterials, die ergonomische Gestaltung der Benutzerschnittstellen und der Erzielung von geringen Anwortzeiten. Diese Aspekte sind eine wichtige Voraussetzung für die Effizienz und Akzeptanz von Software im praktischen Einsatz. Bestehende Fachanwendungen können durch geringen Entwicklungsaufwand einfach in die verteilte Umgebung integriert werden, ohne sie von Grund auf programmieren zu müssen. N2 - Structures are normally unique which often require a new, complete and complex design. The extensiveness and diverseness of the several planning tasks cause a parallel work of the involved planners. Furthermore, the building planning is a creative and iterative process that is characterised by frequent changes of the planning material and coordinations between the professional designers. The planners create different data models with dependencies between each other. The aim of this thesis is to ensure the consistency of the particular expert models by defining dependencies on the basis of object versions. A prerequisite is the development of all specialised applications with the established object-oriented programming paradigm. The sequential and parallel work of many planners is supported by an optimistic access model that does not require write locks. The history of the planning material will be stored additionally and the definition of release states is provided. The software configuration management served as a model for the system architecture whose versioning approach often relies on the client-server concept. The formal description of the used approach is done by the usage of the set theory and relational algebra to ensure its generality and independency from technologies. On the basis of this approach concepts for the application of versioned object models in civil engineering are formulated and verified at a practical scenario with a pilot implementation based on an open source engineering platform. A great importance was attached on the usability of the implementation. This affects especially the structuring of the project material, the ergonomic design of the user interface as well as the achievement of short response times. These aspects are a precondition for the efficiency and acceptance of the software by the practical users. Existing expert applications can be easily integrated in the distributed environment without programming them from scratch. T3 - Informatik in Architektur und Bauwesen - 3 KW - Computer Supported Cooperative Work KW - Objektorientierung KW - Bauplanung KW - Kooperation KW - Verteiltes System KW - Versionsverwaltung KW - Planungsprozess KW - Benut KW - Distributed computing KW - Computer Supported Cooperative Work KW - Object-oriented programming KW - Version control KW - Planning process Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20100115-14935 ER - TY - THES A1 - Tulke, Jan T1 - Kollaborative Terminplanung auf Basis von Bauwerksinformationsmodellen T1 - Collaborative construction scheduling based on building information models N2 - Im Rahmen des sich derzeit vollziehenden Wandels von der segmentierten, zeichnungsorientierten zur integrierten, modellbasierten Arbeitsweise bei der Planung von Bauwerken und ihrer Erstellung werden Computermodelle nicht mehr nur für die physikalische Simulation des Bauwerksverhaltens, sondern auch zur Koordination zwischen den einzelnen Planungsdisziplinen und Projektbeteiligten genutzt. Die gemeinsame Erstellung und Nutzung dieses Modells zur virtuellen Abbildung des Bauwerks und seiner Erstellungsprozesse, das sog. Building Information Modeling (BIM), ist dabei zentraler Bestandteil der Planung. Die Integration der Terminplanung in diese Arbeitsweise erfolgt bisher jedoch nur unzureichend, meist lediglich in der Form einer nachgelagerten 4D-Simulation zur Kommunikation der Planungsergebnisse. Sie weist damit im Verhältnis zum entstehenden Zusatzaufwand einen zu geringen Nutzen für den Terminplaner auf. Gegenstand der vorliegenden Arbeit ist die tiefere Einbettung der Terminplanung in die modellbasierte Arbeitsweise. Auf Basis einer umfassende Analyse der Rahmenbedingungen und des Informationsbedarfs der Terminplanung werden Konzepte zur effizienten Wiederverwendung von im Modell gespeicherten Daten mit Hilfe einer Verknüpfungssprache, zum umfassenden Datenaustausch auf Basis der Industry Foundation Classes (IFC) und für das Änderungsmanagement mittels einer Versionierung auf Objektebene entwickelt.Die für die modellbasierte Terminplanung relevanten Daten und ihre Beziehungen zueinander werden dabei formal beschrieben sowie die Kompatibilität ihrer Granularität durch eine Funktionalität zur Objektteilung sichergestellt. Zur zielgenauen Extraktion von Daten werden zudem Algorithmen für räumliche Anfragen entwickelt. Die vorgestellten Konzepte und ihre Anwendbarkeit werden mittels einer umfangreichen Pilotimplementierung anhand von mehreren Praxisbeispielen demonstriert und somit deren praktische Relevanz und Nutzen nachgewiesen. N2 - In context of the current change from a segmented, drawing based to an integrated, model based planning approach for buildings and their construction processes, computer models are no longer used for physical simulations of structural characteristics only, but also as basis for coordination between different design disciplines and stakeholders. Thereby the collaborative compilation and utilisation of such a model which serves as virtual representation, the so called Building Information Modeling (BIM), is within the core of the new planning approach. But currently, construction sequence planning is only insufficiently integration in this new approach and mostly limited to a subsequent 4D-Simulation for communication of scheduling results. Consequently accruing additional effort for the model use cannot be fully justified by the resulting benefits. Therefore subject of the present thesis is a deeper integration of construction sequence planning into the model based way of working. Starting from a comprehensive analysis of general conditions and information needs during scheduling, concepts of a linking language for efficient reuse of model data, complete data exchange based on Industry Foundation Classes (IFC) and change management based on object versioning are presented. Data used during scheduling and its inherent relationships are described formally and a functionality of object splitting is developed to ensure the compatibility of data granularity. For the sake of target precise data extraction, algorithms of spatial queries are presented. All concepts are implemented in an extensive software package and their practical application is demonstrated by several examples. T3 - Informatik in Architektur und Bauwesen - 4 KW - Terminplanung KW - Scheduling KW - Informationsmodell KW - Kollaboration KW - Modell KW - Versionsverwaltung KW - Bauwesen KW - Teilung KW - Animation KW - Dreidimensionale Comp KW - 4D-Simulation KW - Bauwerksinformationsmodell KW - BIM KW - IFC KW - räumliche Anfragesprache KW - spatial query KW - object splitting KW - Building Information Model KW - construction KW - object versioning Y1 - 2009 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20100805-15135 SN - 978-3-86068-416-0 ER - TY - CHAP A1 - Hauschild, Thomas A1 - Borrmann, André A1 - Hübler, Reinhard T1 - Integration of Constraints into Digital Building Models for Cooperative Planning Processes N2 - The uniqueness and the long life cycle of buildings imply a dynamically modifiable building model. The technological foundation for the management of digital building models, a dynamic model management system (MMS), developed by our research group, allows to explicitly access and to modify the object model of the stored planning data. In this paper, the integration of constraints in digital building models will be shown. Constraints are conditions, which apply to the instances of domain model classes, and are defined by the user at runtime of the information system. For the expression of constraints, the Constraint Modelling Language (CML) has been developed and will be described in this paper. CML is a powerful, intuitively usable object-oriented language, which allows the expression of constraints at a high semantic level. A constrained-enabled MMS can verify, whether an instance fulfils the applying constraints. To ensure flexibility, the evaluation of constraints is not implicitly performed by the systems, but explicitly initiated by the user. A classification of constraint types and example usage scenarios are given. KW - Architektur KW - Verteiltes System KW - Constraint KW - Modellierung Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-1775 ER - TY - CHAP A1 - Hahn, Stephan A1 - Weitzmann, Rüdiger T1 - Nichtlineare Analyse von hybriden Konstruktionen unter Verwendung von selektiv gekoppelten Tragwerks- und Querschnittsmodellen N2 - Bei der Untersuchung hybrider Strukturen kann eine Kopplung von Modellen unterschiedlicher Modellebenen vorteilhaft sein. Durch selektive Kopplung von Tragwerks- und Querschnittsmodellen in ausgewählten Bereichen der Konstruktion kann z.B. eine Verbesserung der Abbildungsgenauigkeit erzielt werden. Dadurch werden erweiterte Aussagen über das Querschnittstragverhalten in extrem beanspruchten Teilen des Tragwerks bei optionaler Skalierbarkeit des Modellumfangs möglich. Im Beitrag werden ausgewählte Varianten der Modellbildung gegenübergestellt und bewertet. Hierbei werden Aspekte der physikalischen Nichtlinearität von hybriden Konstruktionen insbesondere von Stahlbetonkonstruktionen berücksichtigt. Die Einbeziehung von Verfahren der mathematischen Optimierung in die Berechnungsstrategie ermöglicht die Lösung der zugrunde liegenden nichtlinearen Problemstellungen unter Vorgabe von Bemessungszielen und unter Beachtung von Grenzzustandsbedingungen. KW - Tragwerk KW - Stahlbeton KW - Modellierung KW - Bewertungssystem Y1 - 2003 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-3026 ER - TY - CHAP A1 - Ducke, M. A1 - Eckstein, U. A1 - Montag, U. T1 - Die Eisenbahnbrücken des Lehrter Bahnhofs in Berlin - Ein ganzheitliches FE-Berechnungskonzept N2 - Der Komplexität moderner Brückenbauwerke scheinen die verwendeten Berechungsmodelle oft nicht angemessen. Tragwerksberechnungen basieren in vielen Fällen noch auf der Vorgehensweise, das Brückenbauwerk in Einzelbauteile zu zerlegen und mit unterschiedlichen Teilmodellen zu behandeln. Das erscheint, auch vor dem Hintergrund ständig wachsender Rechnerleistung, nicht mehr zeitgemäß. Dies gilt zum Beispiel auch für die gängige Praxis, flächenhafte Brückenüberbauten mit Balkenmodellen zu berechnen. Der vorliegende Beitrag stellt ein ganzheitliches Berech-nungskonzept vor, welches auf der Basis eines einzigen FE-Modells die Berechnung des Gesamtbauwerks erlaubt. Damit wird für alle Bauteile neben der Zustandsgrößenberechnung auch die Bemessung von Stahl- und Spannbetonbauteilen bis hin zu Nachweisen wie zur Beschränkung der Rissbreite geführt. Die Anwendung dieses Berechnungskonzeptes wird am Beispiel der Eisenbahnüberführung des neuen Lehrter Bahn-hofs in Berlin gezeigt. Das verwendete FE-Modell umfasst Baugrund, Fundamente, Stahl- bzw. Gußstahlunterkonstruktion sowie den Stahl- bzw. Spannbetonüberbau. Besonderheiten sind unter anderem die Modellierung des plattenbalkenartigen Überbaus durch exzentrische, vorspannbare Schalenelemente und das getrennte Vorhalten von tragwerks- und lastbezogenen Eingabefiles. Damit gelingt die sequentielle Erfassung unterschiedlicher Bettungsmoduli zur Simulation statischer und dynamischer Beanspruchungen, die Berücksichtigung des Anspannens und der Interaktion zwischen vorgespannten Stahlverbänden zur Aufnahme von Horizontallasten sowie die Berücksichtigung unterschiedlicher statischer Systeme bei der Herstellung des Spannbetonüberbaus. KW - Berlin KW - Eisenbahnbrücke KW - Berechnung KW - Finite-Elemente-Methode KW - Lehrter Bahnhof KW - Gesamtbauwerk Y1 - 2000 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-5812 ER - TY - CHAP A1 - Biehounek, Josef A1 - Grolik, Helmut A1 - Herz, Susanne T1 - Zur Anwendung von Chaos-Entwicklungen in der Tragwerksstatik N2 - Seit mehr als fünfzig Jahren werden zur Untersuchung der Tragwerkssicherheit auch Methoden der Wahrscheinlichkeitsrechnung herangezogen. Ungeachtet der inzwischen erreichten Fortschritte und der offensichtlichen Vorzüge, konnte dieses Vorgehen in der Praxis bis jetzt noch nicht ausreichend Fuß fassen. Im Beitrag wird das Problem der Tragwerkssicherheit mit einem neuartigen Verfahren behandelt. Im Unterschied zu den üblichen probabilistischen Methoden geht es nicht von Verteilungsfunktionen aus. Vielmehr werden die maßgebenden Zufallsgrößen in den Mittelpunkt gestellt und direkt in die Rechenvorschrift eingeführt. Als mathematisches Hilfsmittel dienen die WIENERschen Chaos-Polynome. Sie stellen im Raum der Zufallsgrößen mit beschränkter Varianz eine Basis dar, mit der sich eine beliebige Zufallsgröße nach orthogonalen Polynomen GAUSSscher Zufallsgrößen entwickeln läßt. So entsteht ein effektiver Formalismus, der sich eng an die herkömmliche Deformationsmethode anlehnt und als deren probabilistische Verallgemeinerung angesprochen werden darf. Die Methode liefert die Grenzzustandsbedingung als Funktion der auf das Tragwerk wirkenden Zufallsgrößen. Die Versagenswahrscheinlichkeit kann daher durch Monte-Carlo-Simulation bestimmt werden. Die mit der Auswertung des Wahrscheinlichkeitsintegrals der First Order Reliability Method (FORM) verbundenen Schwierigkeiten werden vermieden. An einem Beispieltragwerk wird dargestellt, wie sich Veränderungen gewisser Konstruktionsparameter auf die Versagenswahrscheinlichkeit auswirken. KW - Baustatik KW - Sicherheit KW - Zufallsvariable KW - Chaostheorie Y1 - 2003 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-2784 ER - TY - CHAP A1 - Soibelman, Lucio A1 - O'Brien, William A1 - Elvin, George T1 - Collaborative Design Processes: A Class on Concurrent Collaboration in Multidisciplinary Design N2 - The rise of concurrent engineering in construction demands early team formation and constant communication throughout the project life cycle, but educational models in architecture, engineering and construction have been slow to adjust to this shift in project organization. Most students in these fields spend the majority of their college years working on individual projects that do not build teamwork or communication skills. Collaborative Design Processes (CDP) is a capstone design course where students from the University of Illinois at Urbana-Champaign and the University of Florida learn methods of collaborative design enhanced by the use of information technology. Students work in multidisciplinary teams to collaborate from remote locations via the Internet on the design of a facility. An innovation of this course compared to previous efforts is that students also develop process designs for the integration of technology into the work of multidisciplinary design teams. The course thus combines both active and reflective learning about collaborative design and methods. The course is designed to provide students the experience, tools, and methods needed to improve design processes and better integrate the use of technology into AEC industry work practices. This paper describes the goals, outcomes and significance of this new, interdisciplinary course for distributed AEC education. Differences from existing efforts and lessons learned to promote collaborative practices are discussed. Principal conclusions are that the course presents effective pedagogy to promote collaborative design methods, but faces challenges in both technology and in traditional intra-disciplinary training of students. KW - Hochschulbildung KW - Entscheidungsunterstützung KW - Computer Supported Cooperative Work Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-1948 ER - TY - CHAP A1 - Keller, Martin A1 - Antoniadis, George A1 - Menzel, Karsten T1 - Resource Management for the Construction Industry N2 - The management of resources is an essential task in each construction company. Today, ERP systems and e-Business systems are available to assist construction companies to efficiently organise the allocation of their personnel and equipment within the company, but they cannot provide the company with the idle resources for every single task that has to be performed during a construction project. Therefore, companies should have an alternative solution to better exploit expensive resources and compensate their fixed costs, but also have them available at the right time for their own business activities. This paper outlines the approach taken by the EU funded project “e-Sharing” (IST-2001-33325) to support resource management between construction companies. It will describe requirements for the management of construction resources, its core features, and the integration approach. Therefore, we will outline the approach of an integrated resource type model supporting the management and classification of construction equipment, construction tasks and qualification profiles. The development is based on a cross-domain analysis and evaluation of existing models. ... KW - Baubetrieb KW - Computerunterstütztes Verfahren KW - Betriebsmittel Y1 - 2004 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-1679 ER -