TY - THES A1 - Fauth, Judith T1 - A process-oriented decision model for determining the permitability of construction projects N2 - In recent years, the discussion of digitalization has arrived in the media, at conferences, and in committees of the construction and real estate industry. While some areas are producing innovations and some contributors can be described as pioneers, other topics still show deficits with regard to digital transformation. The building permit process can also be counted in this category. Regardless of how architects and engineers in planning offices rely on innovative methods, building documents have so far remained in paper form in too many cases, or are printed out after electronic submission to the authority. Existing resources – for example in the form of a building information model, which could provide support in the building permit process – are not being taken advantage of. In order to use digital tools to support decision-making by the building permit authorities, it is necessary to understand the current situation and to question conditions before pursuing the overall automation of internal authority processes as the sole solution. With a substantive-organizational consideration of the relevant areas that influence building permit determination, an improvement of the building permit procedure within authorities is proposed. Complex areas – such as legal situations, the use of technology, as well as the subjective alternative action – are determined and structured. With the development of a model for the determination of building permitability, both an understanding of influencing factors is conveyed and an increase in transparency for all parties involved is created. In addition to an international literature review, an empirical study served as the research method. The empirical study was conducted in the form of qualitative expert interviews in order to determine the current state in the field of building permit procedures. The collected data material was processed and subsequently subjected to a software-supported content analysis. The results were processed, in combination with findings from the literature review, in various analyses to form the basis for a proposed model. The result of the study is a decision model that closes the gap between the current processes within the building authorities and an overall automation of the building permit review process. The model offers support to examiners and applicants in determining building permit eligibility, through its process-oriented structuring of decision-relevant facts. The theoretical model could be transferred into practice in the form of a web application. KW - Baugenehmigung KW - Entscheidungsmodell KW - Bauantrag KW - Prozessmanagement KW - Projektmanagement KW - Building permit KW - Building application KW - Decision-making KW - Process management KW - Project management Y1 - 2021 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20220309-46020 UR - https://e-pub.uni-weimar.de/opus4/frontdoor/index/index/docId/4509 N1 - This work is a translation of the original dissertation (German language) which is accessible at: https://doi.org/10.25643/bauhaus-universitaet.4509 and deposited here as URL link. ER - TY - THES A1 - Fauth, Judith T1 - Ein handlungsorientiertes Entscheidungsmodell zur Feststellung der Genehmigungsfähigkeit von Bauvorhaben N2 - Die Auseinandersetzung mit der Digitalisierung ist in den letzten Jahren in den Medien, auf Konferenzen und in Ausschüssen der Bau- und Immobilienbranche angekommen. Während manche Bereiche Neuerungen hervorbringen und einige Akteure als Pioniere zu bezeichnen sind, weisen andere Themen noch Defizite hinsichtlich der digitalen Transformation auf. Zu dieser Kategorie kann auch das Baugenehmigungsverfahren gezählt werden. Unabhängig davon, wie Architekten und Ingenieure in den Planungsbüros auf innovative Methoden setzen, bleiben die Bauvorlagen bisher zuhauf in Papierform oder werden nach der elektronischen Einreichung in der Behörde ausgedruckt. Vorhandene Ressourcen, beispielsweise in Form eines Bauwerksinformationsmodells, die Unterstützung bei der Baugenehmigungsfeststellung bieten können, werden nicht ausgeschöpft. Um mit digitalen Werkzeugen eine Entscheidungshilfe für die Baugenehmigungsbehörden zu erarbeiten, ist es notwendig, den Ist-Zustand zu verstehen und Gegebenheiten zu hinterfragen, bevor eine Gesamtautomatisierung der innerbehördlichen Vorgänge als alleinige Lösung zu verfolgen ist. Mit einer inhaltlich-organisatorischen Betrachtung der relevanten Bereiche, die Einfluss auf die Baugenehmigungsfeststellung nehmen, wird eine Optimierung des Baugenehmigungsverfahrens in den Behörden angestrebt. Es werden die komplexen Bereiche, wie die Gesetzeslage, der Einsatz von Technologie aber auch die subjektiven Handlungsalternativen, ermittelt und strukturiert. Mit der Entwicklung eines Modells zur Feststellung der Baugenehmigungsfähigkeit wird sowohl ein Verständnis für Einflussfaktoren vermittelt als auch eine Transparenzsteigerung für alle Beteiligten geschaffen. Neben einer internationalen Literaturrecherche diente eine empirische Studie als Untersuchungsmethode. Die empirische Studie wurde in Form von qualitativen Experteninterviews durchgeführt, um den Ist-Zustand im Bereich der Baugenehmigungsverfahren festzustellen. Das erhobene Datenmaterial wurde aufbereitet und anschließend einer softwaregestützten Inhaltsanalyse unterzogen. Die Ergebnisse wurden in Kombination mit den Erkenntnissen der Literaturrecherche in verschiedenen Analysen als Modellgrundlage aufgearbeitet. Ergebnis der Untersuchung stellt ein Entscheidungsmodell dar, welches eine Lücke zwischen den gegenwärtigen Abläufen in den Baubehörden und einer Gesamtautomatisierung der Baugenehmigungsprüfung schließt. Die prozessorientierte Strukturierung entscheidungsrelevanter Sachverhalte im Modell ermöglicht eine Unterstützung bei der Baugenehmigungsfeststellung für Prüfer und Antragsteller. Das theoretische Modell konnte in Form einer Webanwendung in die Praxis übertragen werden. N2 - In recent years, the debate on digitization has been a topic of discussion in the media, at conferences and in committees of the construction and real estate industry. While some areas are producing innovations and some actors can be called pioneers, others still have deficits with regard to the digital transformation. The building permit process can also be considered among this category. Regardless of how architects and engineers use innovative methods in the planning offices, building applications are still often in paper form or are printed out after electronic submission to the authorities. Existing resources, for example in the form of a building information model, which can provide support in obtaining building permits, are not being utilized. In order to develop a decision support for the building authorities with digital tools, it is necessary to understand the actual conditions and to question the circumstances before an overall automation of the internal official processes can be pursued as the sole solution. With a content-based organizational view of the relevant components, which take influence on the building permit determination, an optimization of the building permit procedure in the authorities is aimed at. The complex components, such as the legal situation, the use of technology, but also the subjective alternatives for action, have to be determined and structured. The development of a model for determining building permit ability provides both an understanding of influencing factors and an increase in transparency for all parties involved. In addition to an international literature review, an empirical study served as a method of investigation. The empirical study was conducted in the form of qualitative expert interviews to determine the current state in the field of building permit procedures. The collected data material was prepared and subjected to a software-supported content analysis. In combination with the results of the literature review, the results were processed in various analyses as a model basis. The result of the investigation represents a decision model which closes a gap between the current processes at the building authorities and an overall automation of the building permit review. The process-oriented structuring of decision-relevant factors in the model enables support for the reviewers and the applicants during the building permit assessment. The theoretical model could be transferred into practice in the form of a web application. T3 - Schriften der Professur Baubetrieb und Bauverfahren - 39 KW - Baugenehmigung KW - Entscheidungsmodell KW - Bauantrag KW - Prozessmanagement KW - Projektmanagement KW - Building Permit KW - Decision-making KW - Building application KW - Process management KW - Project management Y1 - 2021 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20210928-45093 UR - https://e-pub.uni-weimar.de/opus4/frontdoor/index/index/docId/4602 SN - 978-3-95773-299-6 N1 - Die englische Übersetzung der Dissertation ist unter https://doi.org/10.25643/bauhaus-universitaet.4602 erfasst und hier als URL Link hinterleg PB - Bauhaus-Universitätsverlag CY - Ilmtal-Weinstraße ER - TY - THES A1 - Leidel, Katja T1 - Ein multikriterielles Entscheidungsmodell zur Risikobewertung von Wasserbauprojekten unter spezieller Betrachtung des indischen Szenarios T1 - A multi-criteria decision model for risk appraisal of hydropower projects with a special focus on Indian scenarios N2 - Die Charakteristiken von Großprojekten werden bei internationaler Bautätigkeit vor allem durch das erhöhte Risiko und die Komplexität infolge länderspezifischer Rahmenbedingungen erweitert. Aufgrund des anwachsenden Konkurrenzkampfes international tätiger Bauunternehmen, müssen die Gewinnmargen jedoch kontinuierlich verringert werden, während Reaktionsfähigkeit, Spezialisierung und Flexibilität vorausgesetzt wird. Daher gewinnt das Risikomanagement und die bewusste Entscheidungsfindung im Umgang mit Risiken verstärkt an Bedeutung. Die zur Verfügung stehenden Risikoanalysetechniken untersuchen zumeist Teilbereiche und stellen in der Regel hohe Anforderungen an den Dateninput. Die Daten können nur aus vorangegangenen Projekten oder aus Expertenurteilen abgeleitet werden. Diese Tatsache steht im Widerspruch zur Einmaligkeit von Bauprojekten und zur schwierigen Beschaffung realer Daten und Einschätzungen von Praxispartnern. Folglich leitet sich der Bedarf nach einer Entscheidungsmethode ab, die den Risikoumfang in seiner Gesamtheit erfassen kann und losgelöst von quantitativen Daten eine Entscheidungsunterstützung herbeiführt. Aus diesem Grund wurde in der vorliegenden Diplomarbeit am Beispiel von identifizierten Risiken für Wasserbauprojekte in Indien ein multikriterielles Entscheidungsmodell entwickelt, dem die Arbeitsweise des Analytic Hierarchy Process (AHP) zugrunde liegt und dessen Umsetzung in Excel 2000 erfolgte. Das Modell strukturiert die Problemsituation anhand einer Risikohierarchie, dient der systematischen Risikobewertung zur Veranschaulichung der relativen Bedeutungen innerhalb des Gesamtrisikoumfangs, beinhaltet ein risikobezogenes Zielsystem zur Bewertung von Risikobehandlungsalternativen und ermöglicht die selbstständige Wahl der Risikobehandlung. Infolge der prozentualen Anteile jeder Risikobehandlung am Gesamtrisikoumfang können Projektstrategien und weitere Erfolgsfaktoren abgeleitet werden. N2 - The characteristics of large-scale projects is enlarged primarily by the increased risk and the complexity because of country specific framework conditions at international construction activity. Due to the growing competition of internationally working contractors the profit margins must be reduced continuously during reaction capacity, specialization, and flexibility is presupposed. Therefore risk management and the conscious decision making in dealing with risks become more and more important. The existing risk analysis techniques focus mainly on specific fragmented areas and make high requirements on data input. The data only can be derived from previous projects or from expert judgments. This fact contradicts the uniqueness of construction projects and the difficult obtaining of real data and assessments of practice partners. Therefore a decision method which can grasp the risk size as a whole and provides a decision support removed from quantitative data is consequently required. For this reason a multi-criteria decision model which is based on the Analytic Hierarchy Process (AHP) was developed referred to identified risks for hydropower projects in India and was carried out in Excel 2000. The model structures the problem situation by means of a risk hierarchy, serves the systematic risk assessment to demonstrate the relative importance within the complete risk size, contains a risk-related target system for the assessment of risk treatment alternatives and makes the independent choice of the risk treatment possible. As a result of the proportional shares of every risk treatment alternative in the complete risk size the project strategy and additional success factors can be derived. KW - Entscheidungsunterstützung KW - Entscheidungsfindung KW - Entscheidungsprozess KW - Entscheidungsmodell KW - Analytic Hierarchy Process KW - Risikomanagement KW - Risik KW - Wasserbauprojekte KW - Indien KW - internationale Bauprojekte KW - decision making KW - risk KW - risk appraisal KW - Analytic Hierarchy Process KW - hydropower KW - India Y1 - 2005 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20111215-6574 N1 - Der Volltext-Zugang wurde im Zusammenhang mit der Klärung urheberrechtlicher Fragen mit sofortiger Wirkung gesperrt. ER -