TY - THES A1 - Fauth, Judith T1 - A process-oriented decision model for determining the permitability of construction projects N2 - In recent years, the discussion of digitalization has arrived in the media, at conferences, and in committees of the construction and real estate industry. While some areas are producing innovations and some contributors can be described as pioneers, other topics still show deficits with regard to digital transformation. The building permit process can also be counted in this category. Regardless of how architects and engineers in planning offices rely on innovative methods, building documents have so far remained in paper form in too many cases, or are printed out after electronic submission to the authority. Existing resources – for example in the form of a building information model, which could provide support in the building permit process – are not being taken advantage of. In order to use digital tools to support decision-making by the building permit authorities, it is necessary to understand the current situation and to question conditions before pursuing the overall automation of internal authority processes as the sole solution. With a substantive-organizational consideration of the relevant areas that influence building permit determination, an improvement of the building permit procedure within authorities is proposed. Complex areas – such as legal situations, the use of technology, as well as the subjective alternative action – are determined and structured. With the development of a model for the determination of building permitability, both an understanding of influencing factors is conveyed and an increase in transparency for all parties involved is created. In addition to an international literature review, an empirical study served as the research method. The empirical study was conducted in the form of qualitative expert interviews in order to determine the current state in the field of building permit procedures. The collected data material was processed and subsequently subjected to a software-supported content analysis. The results were processed, in combination with findings from the literature review, in various analyses to form the basis for a proposed model. The result of the study is a decision model that closes the gap between the current processes within the building authorities and an overall automation of the building permit review process. The model offers support to examiners and applicants in determining building permit eligibility, through its process-oriented structuring of decision-relevant facts. The theoretical model could be transferred into practice in the form of a web application. KW - Baugenehmigung KW - Entscheidungsmodell KW - Bauantrag KW - Prozessmanagement KW - Projektmanagement KW - Building permit KW - Building application KW - Decision-making KW - Process management KW - Project management Y1 - 2021 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20220309-46020 UR - https://e-pub.uni-weimar.de/opus4/frontdoor/index/index/docId/4509 N1 - This work is a translation of the original dissertation (German language) which is accessible at: https://doi.org/10.25643/bauhaus-universitaet.4509 and deposited here as URL link. ER - TY - THES A1 - Fauth, Judith T1 - Ein handlungsorientiertes Entscheidungsmodell zur Feststellung der Genehmigungsfähigkeit von Bauvorhaben N2 - Die Auseinandersetzung mit der Digitalisierung ist in den letzten Jahren in den Medien, auf Konferenzen und in Ausschüssen der Bau- und Immobilienbranche angekommen. Während manche Bereiche Neuerungen hervorbringen und einige Akteure als Pioniere zu bezeichnen sind, weisen andere Themen noch Defizite hinsichtlich der digitalen Transformation auf. Zu dieser Kategorie kann auch das Baugenehmigungsverfahren gezählt werden. Unabhängig davon, wie Architekten und Ingenieure in den Planungsbüros auf innovative Methoden setzen, bleiben die Bauvorlagen bisher zuhauf in Papierform oder werden nach der elektronischen Einreichung in der Behörde ausgedruckt. Vorhandene Ressourcen, beispielsweise in Form eines Bauwerksinformationsmodells, die Unterstützung bei der Baugenehmigungsfeststellung bieten können, werden nicht ausgeschöpft. Um mit digitalen Werkzeugen eine Entscheidungshilfe für die Baugenehmigungsbehörden zu erarbeiten, ist es notwendig, den Ist-Zustand zu verstehen und Gegebenheiten zu hinterfragen, bevor eine Gesamtautomatisierung der innerbehördlichen Vorgänge als alleinige Lösung zu verfolgen ist. Mit einer inhaltlich-organisatorischen Betrachtung der relevanten Bereiche, die Einfluss auf die Baugenehmigungsfeststellung nehmen, wird eine Optimierung des Baugenehmigungsverfahrens in den Behörden angestrebt. Es werden die komplexen Bereiche, wie die Gesetzeslage, der Einsatz von Technologie aber auch die subjektiven Handlungsalternativen, ermittelt und strukturiert. Mit der Entwicklung eines Modells zur Feststellung der Baugenehmigungsfähigkeit wird sowohl ein Verständnis für Einflussfaktoren vermittelt als auch eine Transparenzsteigerung für alle Beteiligten geschaffen. Neben einer internationalen Literaturrecherche diente eine empirische Studie als Untersuchungsmethode. Die empirische Studie wurde in Form von qualitativen Experteninterviews durchgeführt, um den Ist-Zustand im Bereich der Baugenehmigungsverfahren festzustellen. Das erhobene Datenmaterial wurde aufbereitet und anschließend einer softwaregestützten Inhaltsanalyse unterzogen. Die Ergebnisse wurden in Kombination mit den Erkenntnissen der Literaturrecherche in verschiedenen Analysen als Modellgrundlage aufgearbeitet. Ergebnis der Untersuchung stellt ein Entscheidungsmodell dar, welches eine Lücke zwischen den gegenwärtigen Abläufen in den Baubehörden und einer Gesamtautomatisierung der Baugenehmigungsprüfung schließt. Die prozessorientierte Strukturierung entscheidungsrelevanter Sachverhalte im Modell ermöglicht eine Unterstützung bei der Baugenehmigungsfeststellung für Prüfer und Antragsteller. Das theoretische Modell konnte in Form einer Webanwendung in die Praxis übertragen werden. N2 - In recent years, the debate on digitization has been a topic of discussion in the media, at conferences and in committees of the construction and real estate industry. While some areas are producing innovations and some actors can be called pioneers, others still have deficits with regard to the digital transformation. The building permit process can also be considered among this category. Regardless of how architects and engineers use innovative methods in the planning offices, building applications are still often in paper form or are printed out after electronic submission to the authorities. Existing resources, for example in the form of a building information model, which can provide support in obtaining building permits, are not being utilized. In order to develop a decision support for the building authorities with digital tools, it is necessary to understand the actual conditions and to question the circumstances before an overall automation of the internal official processes can be pursued as the sole solution. With a content-based organizational view of the relevant components, which take influence on the building permit determination, an optimization of the building permit procedure in the authorities is aimed at. The complex components, such as the legal situation, the use of technology, but also the subjective alternatives for action, have to be determined and structured. The development of a model for determining building permit ability provides both an understanding of influencing factors and an increase in transparency for all parties involved. In addition to an international literature review, an empirical study served as a method of investigation. The empirical study was conducted in the form of qualitative expert interviews to determine the current state in the field of building permit procedures. The collected data material was prepared and subjected to a software-supported content analysis. In combination with the results of the literature review, the results were processed in various analyses as a model basis. The result of the investigation represents a decision model which closes a gap between the current processes at the building authorities and an overall automation of the building permit review. The process-oriented structuring of decision-relevant factors in the model enables support for the reviewers and the applicants during the building permit assessment. The theoretical model could be transferred into practice in the form of a web application. T3 - Schriften der Professur Baubetrieb und Bauverfahren - 39 KW - Baugenehmigung KW - Entscheidungsmodell KW - Bauantrag KW - Prozessmanagement KW - Projektmanagement KW - Building Permit KW - Decision-making KW - Building application KW - Process management KW - Project management Y1 - 2021 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20210928-45093 UR - https://e-pub.uni-weimar.de/opus4/frontdoor/index/index/docId/4602 SN - 978-3-95773-299-6 N1 - Die englische Übersetzung der Dissertation ist unter https://doi.org/10.25643/bauhaus-universitaet.4602 erfasst und hier als URL Link hinterleg PB - Bauhaus-Universitätsverlag CY - Ilmtal-Weinstraße ER - TY - THES A1 - Hörold, Stefan T1 - Leistungsbezogene Musterjahresganglinien für den Straßenbetriebsdienst N2 - In den letzten Jahrzehnten unterlag der Straßenbetriebsdienst tiefgreifenden Veränderungen. Diese Veränderungen schließt auch die betriebliche Steuerungsphilosophie ein, um eine planungsrationale und ökonomische Gestaltung des Straßenbetriebsdienstes zu unterstützen. Dabei erfolgt eine verbindliche Vorgabe der Leistungsinhalte und -umfänge und ermöglicht eine Budgetierung für das vorgesehene Jahresarbeitsprogramm. Ziel der Untersuchung ist die Entwicklung eines Modells für die Ermittlung von leistungsbezogenen Musterjahresganglinien zur Unterstützung der Jahresarbeitsplanung. Dafür lagen für jede Leistung des Leistungsbereiches „Grünpflege“ jeweils 260 einzelne Jahresganglinien vor. Im Ergebnis der Untersuchung wird die leistungsbezogene Musterjahresganglinie in vier Schritten ermittelt. Im ersten Schritt erfolgt die Prüfung der Datenqualität; im zweiten Schritt eine Korrelationsanalyse; im dritten Schritt die fachliche Überprüfung der Leistungsausprägung und im vierten Schritt die Ermittlung der leistungsbezogenen Musterjahresganglinie aus den verbliebenen leistungsbezogenen Jahresganglinien. T3 - Schriften der Professur Baubetrieb und Bauverfahren - 40 KW - Straßenbetriebsdienst KW - Budgetierung KW - Arbeitsplanung KW - Ergebnisorientierte Steuerung KW - Musterjahresganglinien KW - Jahresarbeitsplanung Y1 - 2021 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20210830-44910 ER - TY - THES A1 - Mukherjee, Nilangshu T1 - A numerical comparison of the impact of different climatic conditions in different geographic locations on the construction of an office building N2 - The aim of my research is to observe the variance of energy efficiency of a typical multi-story office building under the exposure of different climatic conditions. Energy efficiency requirements in building codes or energy standards are among the most important single measures for buildings’ energy efficiency. Therefore, this study can be set up for a better understanding of how energy efficiency of a building changes under the effect of adverse to moderate climatic conditions which possess a mentionable effect on the operation of a building. This thesis is structured in three balanced and conceptual steps. Following the aim of the project, the virtual building model is to be analyzed under the effect of seven distinct climatic conditions namely work environment of New Delhi, Mumbai, Berlin, Lisbon, Copenhagen, Dubai and Montreal. Firstly, the task is to do a complete literature research based on the scope of similar researches and studying the problems in detail along with the theoritical background all the concepts which are implemented to get the numerical results. This chapter also comprises a detailed study of the climatic conditions of the above-mentioned cities. Different climatic traits like temperature variations, count of heating and cooling degree days, relative humidity, temperature range and comfort zonal charts for the specified cities are studied in detail. This study helps to understand the effect of these adverse to moderate climates on the operation of the building. On the second step, the virtual building model is prepared on a software platform named Revit Structures. This virtual building model is not necessarily a complete building, but it has the relevant functionalities of a real building. We perform the energy analysis and the heating and cooling analysis on this virtual building model to study the operational outcome of the building under different climatic conditions in detail. By the end of these above two tasks, two scenarios are observed. On one hand, we have a literature research and on the other hand we have the numerical results. Therefore, finally we present a comparative scenario based on the energy efficient performances of the building under such variant climatic conditions. This is followed by the prediction of thermal comfort level inside the building and it based on Fanger’s PMV Model. Understanding the literature and the numerical values in detail helps us to predict the index thermal comfort level inside the building. The conclusion of this master thesis focuses mainly on the scopes of improvement of energy efficiency requirements in energy codes if any, differentiated according to specific locations. The initial aim of my hypothesis which is to study the impacts of climatic variations on the energy efficient performances of a building is fulfilled but as such topics have very deep and broad roots, the scope of further improvements is always predominant. KW - Klima KW - Energieeffizienz KW - Climatic conditions KW - Building performance Y1 - 2017 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170811-32700 ER - TY - JOUR A1 - Bargstädt, Hans-Joachim T1 - Challenges of BIM for Construction Site Operations JF - Procedia Engineering N2 - Building Information Modeling is a powerful tool for the design and for a consistent set of data in a virtual storage. For the application in the phases of realization and on site it needs further development. The paper describes main challenges and main features, which will help the development of software to better service the needs of construction site managers KW - Building Information Modeling KW - Baustelle KW - BIM; Building Information Modeling; site management; construction site. Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170413-31218 SP - 52 EP - 59 ER - TY - THES A1 - Steinkrauß, Tobias T1 - Building Information Modeling im Erdbau - eine Potentialanalyse im Spezialtiefbau N2 - Jede Baumaßnahme ist durch einen Unikatcharakter geprägt. Individuelle Planung, Vergabe und Bauvorgänge stellen immer wieder aufs Neue eine große Herausforderung dar. Durch die sich teilweise sehr schnell ändernden Randbedingungen, müssen erarbeitete Abläufe häufig schnell geändert werden. Dies geschieht heutzutage meist auf Grundlage von Erfahrungen der am Bau Beteiligten. Auch bei bester Planung und Vorbereitung können Unwägbarkeiten den Bauprozess aufhalten. Das können ungeeigneter Baugrund, verschiedenste Hinderungen im Baufeld, schlechte Witterungsverhältnisse, Ausfälle von Maschinen, veränderte Zielsetzungen des Auftraggebers und vieles mehr sein. Dies führt zu Bauzeitverlängerungen und damit zu Kostensteigerungen. Um diesen Problemen besser begegnen zu können und diesen komplexen und fehler-anfälligen Prozess zu unterstützen, sind ein verbesserter Informationsfluss, genauere Boden-aufschlüsse und eine exaktere Dimensionierung des einzusetzenden Gerätes notwendig. Aus diesen Gründen ist der Einsatz von Building Information Modeling (BIM) sinnvoll. BIM bietet die Möglichkeit den Informationsfluss zu verbessern, die Datengenauigkeit zu erhöhen und Abläufe zu optimieren. Außerdem ermöglicht die Anwendung Planungsschritte miteinander zu verknüpfen, Kalkulationen zu vereinfachen und das Erstellen eines intelligenten Modells, das über den gesamten Lebenszyklus erweitert werden kann. Die Maßnahmen des Spezialtiefbaus zählen zu den kostenintensivsten auf einer Baustelle. Großes Gerät und spezialisierte Firmen sind für eine erfolgreiche Durchführung unerlässlich. Da der Baugrund immer einen großen Unsicherheitsfaktor bildet, müssen geeignete, unterstützende Anwendungen zum Einsatz kommen. Hierfür bildet BIM eine geeignete Plattform. Protokolle, Maschinendaten und Kontrolldaten können hier webbasiert analysiert und für alle zugänglich gemacht werden, um zum einen die Transparenz zu steigern und zum anderen den Überblick, selbst bei hochkomplexen Bauvorhaben zu behalten. In dieser Arbeit soll ein Überblick über die aktuelle Forschungssituation im Bereich Building Information Modeling im Erdbau, speziell im Spezialtiefbau, gegeben werden. Die Ergebnisse die mit Hilfe vorhandener Publikationen und Forschungsarbeiten verschiedener Universitäten und namhafter Forschungsgruppen zusammengetragen wurden sollen eine Grundlage für die weitere Forschung in diesem Bereich bilden. Über die Aufgabenstellung hinaus wird zusätzlich mit dem Softwareprogramm Revit 2014 ein Modell erstellt. Es wird versucht eine überschnittene Bohrpfahlwand zu modellieren und sie mit Parametern auszustatten. Zusammenfassend wird das Programm für den Einsatz bewertet. KW - BIM KW - Erdbau KW - Spezialtiefbau KW - Building Information Modeling Y1 - 2016 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20160623-26140 ER - TY - THES A1 - Kratt, Helen T1 - Building Information Modeling im Erdbau - eine Potentialanalyse im Tiefbau N2 - Die meisten Baustellen bieten Optimierungspotential. Vor allem der Erdbau fordert durch seine hohe Dynamik und großen Unsicherheiten eine hohe Planungsleistung für jedes neue Projekt. Doch auch bei bester Planung und Vorbereitung kann der Bauprozess durch nicht vorhersehbare Einwirkungen aufgehalten werden. Dazu zählen Witterungseinflüsse, Baumaschinenausfälle, unvorhergesehene Bodenschichten und veränderte Zielsetzungen des Auftraggebers. Dies kann zu Störungen im Bauablauf führen, die eine Bauzeitverzögerung und eine Kostensteigerung nach sich ziehen. Um diese Probleme zu umgehen, sind ein verbesserter Informationsfluss, genaue Bodenaufschlüsse und eine exakte Dimensionierung des einzusetzenden Gerätes notwendig. Hier kann Building Information Modeling (BIM) zum Einsatz kommen. Diese Anwendung bietet die Möglichkeit, die Datengenauigkeit zu erhöhen, den Informationsfluss auf der Baustelle zu verbessern, eine Informationsplattform für alle Beteiligten zu schaffen und die Abläufe transparent zu gestalten. Außerdem ermöglicht die Anwendung Planungsschritte miteinander zu verknüpfen, Kalkulationen zu vereinfachen und das Erstellen eines intelligenten Modells, das über den gesamten Lebenszyklus erweitert werden kann. Die Grundlagen dieser Arbeit bilden die Begriffsdefinitionen zu Erdbau, Tiefbau und Building Information Modeling. Diese Arbeit setzt sich speziell mit Erdbauwerken und deren Sicherungsmaßnahmen auseinander. Darauf aufbauend wird im Rahmen einer Recherche der Forschungsstand im Bereich Building Information Modeling und Tiefbau zusammengefasst. Mit Hilfe einiger Forschungsbeiträge, -projekte, -verbände, Dissertationen und Anwendungsprogrammen wird ein Überblick geschaffen. Die Übersicht soll eine Grundlage für die weitere Forschung auf diesem Gebiet bilden. Abschließend findet eine Bewertung statt. Über die Aufgabenstellung hinaus wird zusätzlich mit dem Softwareprogramm Revit 2014 ein Modell erstellt, um aufzuzeigen, dass das Potential auf Erdbaustellen mit BIM-Anwendungen besser ausgeschöpft werden kann. Es wird versucht eine Gabionenwand, eine Sicherungsmaßnahme von Erdbauwerken zu modellieren und sie mit Parametern auszustatten. Zusammenfassend wird das Programm für den Einsatz im Tiefbau bewertet. KW - BIM KW - Erdbau KW - Tiefbau KW - Building Information Modeling Y1 - 2016 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20160623-26132 ER - TY - CHAP ED - Gürlebeck, Klaus ED - Lahmer, Tom T1 - International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering : July 20 - 22 2015, Bauhaus-University Weimar T1 - Internationales Kolloquium über Anwendungen der Informatik und Mathematik in Architektur und Bauwesen : 20. bis 22.7. 2015, Bauhaus-Universität Weimar T2 - Digital Proceedings, International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering : July 20 - 22 2015, Bauhaus-University Weimar N2 - The 20th International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering will be held at the Bauhaus University Weimar from 20th till 22nd July 2015. Architects, computer scientists, mathematicians, and engineers from all over the world will meet in Weimar for an interdisciplinary exchange of experiences, to report on their results in research, development and practice and to discuss. The conference covers a broad range of research areas: numerical analysis, function theoretic methods, partial differential equations, continuum mechanics, engineering applications, coupled problems, computer sciences, and related topics. Several plenary lectures in aforementioned areas will take place during the conference. We invite architects, engineers, designers, computer scientists, mathematicians, planners, project managers, and software developers from business, science and research to participate in the conference! KW - Angewandte Informatik KW - Angewandte Mathematik KW - Computerunterstütztes Verfahren KW - Building Information Modeling KW - Optimization in engineering applications KW - Data, information and knowledge modeling in civil engineering KW - Function theoretic methods and PDE in engineering sciences KW - Mathematical methods for (robotics and) computer vision KW - Numerical modeling in engineering Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20150828-24515 SN - 1611-4086 ER - TY - THES A1 - Goedicke, Glenn T1 - Mögliche Schnittstellenverschiebungen zwischen Bau- und Nebentätigkeiten auf ausdifferenzierten Baustellen aus arbeitsrechtlicher Sicht N2 - In der modernen Arbeitswelt ist es üblich betriebliche Aufgaben extern zu vergeben. Dieser Vorgang wird in der Wirtschaft Outsourcing genannt und beschränkt sich in der Regel auf Arbeiten, welche nicht zu den Kernkompetenzen eines Unternehmens gehören. Wenn diese Arbeiten durch spezialisierte Unternehmen übernommen werden ergeben sich Potenziale, die weit über eine bloße Kostensenkung hinausgehen. Der Kern dieser Arbeit bezieht sich auf die Auslagerung von sogenannten Nebentätigkeiten im Zusammenhang einer Bauwerksausführung. Dabei werden die arbeitsrechtliche Situation, Machbarkeit und Sinnhaftigkeit analysiert. Das Arbeitsrecht im Baugewerbe ist überaus komplex und von starren Regelungen geprägt. Die für allgemeinverbindlich erklärten Tarifverträge gelten gemeinhin für alle Betriebe, die überwiegend bauliche Tätigkeiten ausüben. Problematisch wird die tarifliche Zuordnung für Betriebe, welche die Nebentätigkeiten übernehmen und für gewöhnlich nicht in den Geltungsbereich der Tarifverträge fallen. Bei der Vergabe von Nebentätigkeiten mit Hilfe von Werk- oder Dienstverträgen bedarf es einer genauen Klärung, ab wann eine unerlaubte Arbeitnehmerüberlassung beginnt. Im Rahmen dieser Arbeit soll untersucht werden, inwieweit eine Auslagerung der baulichen Nebentätigkeiten durch eine Werk- oder Dienstvertragsvergabe an die Grenzen der arbeitsrechtlichen Gegebenheiten stößt. Zusätzlich wird eine tarifliche Einordnung der Tätigkeiten vorgenommen. KW - Arbeitsrecht KW - Leiharbeit KW - Outsourcing Y1 - 2015 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20150629-24192 ER - TY - THES A1 - Dang, Trang T1 - Automated Detailing of 4D Schedules N2 - The increasing success of BIM (Building Information Model) and the emergence of its implementation in 3D construction models have paved a way for improving scheduling process. The recent research on application of BIM in scheduling has focused on quantity take-off, duration estimation for individual trades, schedule visualization, and clash detection. Several experiments indicated that the lack of detailed planning causes about 30% non-productive time and stacking of trades. However, detailed planning still has not been implemented in practice despite receiving a lot of interest from researchers. The reason is associated with the huge amount and complexity of input data. In order to create a detailed planning, it is time consuming to manually decompose activities, collect and calculate the detailed information in relevant. Moreover, the coordination of detailed activities requires much effort for dealing with their complex constraints. This dissertation aims to support the generation of detailed schedules from a rough schedule. It proposes a model for automated detailing of 4D schedules by integrating BIM, simulation and Pareto-based optimization. T3 - Schriften der Professur Baubetrieb und Bauverfahren - 32 KW - BIM KW - Simulation KW - Pareto optimization KW - multi-objective optimization KW - scheduling Y1 - 2014 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20141006-23103 ER -