TY - CHAP A1 - Hamm, Matthias A1 - Beißert, Ulrike A1 - König, Markus ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - SIMULATION-BASED OPTIMIZATION OF CONSTRUCTION SCHEDULES BY USING PARETO SIMULATED ANNEALING N2 - Within the scheduling of construction projects, different, partly conflicting objectives have to be considered. The specification of an efficient construction schedule is a challenging task, which leads to a NP-hard multi-criteria optimization problem. In the past decades, so-called metaheuristics have been developed for scheduling problems to find near-optimal solutions in reasonable time. This paper presents a Simulated Annealing concept to determine near-optimal construction schedules. Simulated Annealing is a well-known metaheuristic optimization approach for solving complex combinatorial problems. To enable dealing with several optimization objectives the Pareto optimization concept is applied. Thus, the optimization result is a set of Pareto-optimal schedules, which can be analyzed for selecting exactly one practicable and reasonable schedule. A flexible constraint-based simulation approach is used to generate possible neighboring solutions very quickly during the optimization process. The essential aspects of the developed Pareto Simulated Annealing concept are presented in detail. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28499 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Nikulla, Susanne ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - INFLUENCE OF THE ABSTRACTION LEVEL IN KINEMATICAL MODELS OF FINITE ELEMENT FORMULATIONS N2 - Nonlinear analyses are characterised by approximations of the fundamental equations in different quality. Starting with a general description of nonlinear finite element formulation the fundamental equations are derived for plane truss elements. Special emphasis is placed on the determination of internal and external system energy as well as influence of different quality approaches for the displacement-strain relationship on solution quality. To simplify the solution procedure the nonlinear function describing the kinematics is expanded into a Taylor series and truncated after the n-th series term. The different kinematics influence speed of convergence as well as exactness of solution. On a simple truss structure this influence is shown. To assess the quality of different formulations concerning the nonlinear kinematic equation three approaches are discussed. First the overall internal and external energy is compared for different kinematical models. In a second step the energy content related to single terms describing displacement-strain relationship is investigated and used for quality control following two different paths. Based on single ε-terms an adaptive scheme is used to change the kinematical model depending on increasing nonlinearity of the structure. The solution quality has turned out satisfactory compared to the exact result. More detailed investigations are necessary to find criteria for the threshold values for the iterative process as well as for decision on number and step size of incremental load steps. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28780 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Castillo-Pérez, Raúl ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - AN APPLICATION OF FORMAL POWER SERIES FOR THE DEVELOPMENT OF OPTICAL FILTERS N2 - The application of a recent method using formal power series is proposed. It is based on a new representation for solutions of Sturm-Liouville equations. This method is used to calculate the transmittance and reflectance coefficients of finite inhomogeneous layers with high accuracy and efficiency. Tailoring the refraction index profile defining the inhomogeneous media it is possible to develop very important applications such as optical filters. A number of profiles were evaluated and then some of them selected in order to perform an improvement of their characteristics via the modification of their profiles. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28354 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Chudoba, Rostislav A1 - Scholzen, A. A1 - Hegger, Josef ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - MICROPLANE MODEL WITH INITIAL AND DAMAGE-INDUCED ANISOTROPY APPLIED TO TEXTILE-REINFORCED CONCRETE N2 - The presented material model reproduces the anisotropic characteristics of textile reinforced concrete in a smeared manner. This includes both the initial anisotropy introduced by the textile reinforcement, as well as the anisotropic damage evolution reflecting fine patterns of crack bridges. The model is based on the microplane approach. The direction-dependent representation of the material structure into oriented microplanes provides a flexible way to introduce the initial anisotropy. The microplanes oriented in a yarn direction are associated with modified damage laws that reflect the tension-stiffening effect due to the multiple cracking of the matrix along the yarn. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28367 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Stein, Peter ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - NURBS-BASED ELEMENTS AS A BASIS FOR INTEGRATING ENGINEERING APPLICATIONS N2 - Building information modeling offers a huge potential for increasing the productivity and quality of construction planning processes. Despite its promising concept, this approach has not found widespread use. One of the reasons is the insufficient coupling of the structural models with the general building model. Instead, structural engineers usually set up a structural model that is independent from the building model and consists of mechanical models of reduced dimension. An automatic model generation, which would be valuable in case of model revisions is therefore not possible. This can be overcome by a volumetric formulation of the problem. A recent approach employed the p-version of the finite element method to this problem. This method, in conjunction with a volumetric formulation is suited to simulate the structural behaviour of both „thick“ solid bodies and thin-walled structures. However, there remains a notable discretization error in the numerical models. This paper therefore proposes a new approach for overcoming this situation. It sugggests the combination of the Isogeometric analysis together with the volumetric models in order to integrate the structural design into the digital, building model-centered planning process and reduce the discretization error. The concept of the isogeometric analysis consists, roughly, in the application of NURBS functions to represent the geometry and the shape functions of the elements. These functions possess some beneficial properties regarding numerical simulation. Their use, however, leads to some intricacies related to the setup of the stiffness matrix. This paper describes some of these properties. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28944 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Lahmer, Tom ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - HYDRO-MECHANICAL COUPLED FIELD SYSTEM IDENTIFICATION - APPLICATION TO WATER RESERVOIRS N2 - In this paper we present an inverse method which is capable of identifying system components in a hydro-mechanically coupled system, i.e. for fluid flow in porous media. As an example we regard water dams that were constructed more than hundred years ago but which are still in use. Over the time ageing processes have changed the condition of these dams. Within the dams fissures might have grown. The proposed method is designed to locate these fissures out of combined mechanical and hydraulic measurements. In a numerical example the fissures or damaged zones are described by a smeared crack model. The task is now to identify simultaneously the spatial distribution of Young’s modulus and the hydraulic permeability due to the fact, that in regions where damages are present, the mechanical stiffness of the system is reduced and the permeability increased. The inversion is shown to be an ill-posed problem. As a consequence regularizing methods have to be applied, where the nonlinear Landweber method (a gradient type method combined with a discrepancy principle) has proven to be an efficient choice. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28650 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Huhnt, Wolfgang A1 - Richter, Sven ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - Modification Management for Planning and Construction Processes N2 - Planning and construction processes are characterized by the peculiarity that they need to be designed individually for each project. It is necessary to set up an individual schedule for each project. As a basis for a new project, schedules from already finished projects are used, but adaptions are always necessary. In practice, scheduling tools only document a process. Schedules cover a set of activities, their duration and a set of interdependencies between activities. The design of a process is up to the user. It is not necessary to specify each interdependency, and completeness and correctness need to be checked manually. No methodologies are available to guarantee properties such as correctness or completeness. The considerations presented in the paper are based on an approach where a planning and a construction process including the interdependencies between planning and construction activities are regarded as a result. Selected information need to be specified by a user, and a proposal for an order of planning and construction activities is computed. As a consequence, process properties such as correctness and completeness can be guaranteed with respect to user input. Especially in Germany, clients are allowed to modify their requirements at any time. This leads to modifications in the planning and construction processes. This paper covers a mathematical formulation for this problem based on set theory. A complex structure is set up covering objects and relations; and operations are defined that guarantee consistency in the underlying and versioned process description. The presented considerations are based on previous work. This paper can be regarded as the next step in a series of previous work describing how a suitable concept for handling, planning and construction processes in civil engineering can be formed. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28510 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Sharmak, Wael A1 - Scherer, Raimar J. ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - ADAPTABLE PROJECT MANAGEMENT PLANS USING CHANGE TEMPLATES-BASED APPROACH N2 - The uncertainty existing in the construction industry is bigger than in other industries. Consequently, most construction projects do not go totally as planned. The project management plan needs therefore to be adapted repeatedly within the project lifecycle to suit the actual project conditions. Generally, the risks of change in the project management plan are difficult to be identified in advance, especially if these risks are caused by unexpected events such as human errors or changes in the client preferences. The knowledge acquired from different resources is essential to identify the probable deviations as well as to find proper solutions to the faced change risks. Hence, it is necessary to have a knowledge base that contains known solutions for the common exceptional cases that may cause changes in each construction domain. The ongoing research work presented in this paper uses the process modeling technique of Event-driven Process Chains to describe different patterns of structure changes in the schedule networks. This results in several so called “change templates”. Under each template different types of change risk/ response pairs can be categorized and stored in a knowledge base. This knowledge base is described as an ontology model populated with reference construction process data. The implementation of the developed approach can be seen as an iterative scheduling cycle that will be repeated within the project lifecycle as new change risks surface. This can help to check the availability of ready solutions in the knowledge base for the situation at hand. Moreover, if the solution is adopted, CPSP, “Change Project Schedule Plan „a prototype developed for the purpose of this research work, will be used to make the needed structure changes of the schedule network automatically based on the change template. What-If scenarios can be implemented using the CPSP prototype in the planning phase to study the effect of specific situations without endangering the success of the project objectives. Hence, better designed and more maintainable project schedules can be achieved. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28886 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Reuter, Markus ED - Gürlebeck, Klaus ED - Könke, Carsten T1 - EVALUATION OF THE ANALYSIS METHOD FOR THE DESIGN OF FRAME STRUCTURES N2 - By the use of numerical methods and the rapid development of computer technology in the recent years, a large variety, complexity, refinement and capability of partial models have been achieved. This can be noticed in the evaluation of the reliability of structures, e.g. the increased use of spatial structural systems. For the different fields of civil engineering, well developed partial models already exist. Because these partial models are most often used separately, the general view is not entirely illustrated. Until now, there has been no common methodology for evaluating the efficiency of models; the trust in the prediction of a special engineering model has generally relied on the engineer’s experience. In this paper the basics of evaluation of simple models and coupled partial models of frame structures will be discussed using sustainable numerical methods. Furthermore, quality classes (levels) of design tasks will be defined based on their practical relevance. In addition, analysis methods will be systemized. After analysis of different published assessment methods, it may be noted, that the Efficiency Indicator Method (EWM) is most suitable for the observed evaluation problem. Therefore, the EWM was modified to the Model Efficiency Analysis (MEA) for the purpose of a holistic evaluation. The criteria are characterized by two groups, benefit and expenditure, and it is possible by calculating the quotient (benefit/expenditure) to make a statement about the efficiency of the observed models. Presently, the expenditure value is not a subject of investigation, and so the model efficiency is calculated only by the benefit value. This paper also contains the associated criteria catalog, different normalization methods, as well as weighting possibilities. KW - Angewandte Informatik KW - Angewandte Mathematik KW - Architektur KW - Computerunterstütztes Verfahren KW - Computer Science Models in Engineering; Multiscale and Multiphysical Models; Scientific Computing Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20170314-28823 UR - http://euklid.bauing.uni-weimar.de/ikm2009/paper.html SN - 1611-4086 ER - TY - CHAP A1 - Theiler, Michael A1 - Tauscher, Eike A1 - Tulke, Jan A1 - Riedel, Thomas ED - Krämer, Torsten T1 - Boolesche Operationen für die Visualisierung von IFC-Gebäudemodellen T2 - Forum Bauinformatik 2010 N2 - Die Planung von komplexen Bauwerken erfolgt zunehmend mit Planungswerkzeugen, die den Export von Bauwerksinformationen im STEP-Format auf Grundlage der IFC (Industry Foundation Classes) erlauben. Durch die Verfügbarkeit dieser Schnittstelle ist es möglich, Bauwerksinformationen für die weiterführende Verarbeitung zu verwenden. Zur Visualisierung der geometrischen Daten stehen innerhalb der IFC verschiedene geometrische Modelle für die Darstellung von Bauteilen zur Verfügung. Unter anderem werden für das „Ausschneiden“ von Öffnungen aus Bauteilen (z.B. für Fenster und Türen) geometrische boolesche Operationen benötigt. Gegenstand des Beitrags ist die Vorstellung eines Algorithmus zur Berechnung von booleschen Operationen auf Basis eines triangulierten B-Rep (Boundary Representation) Modells nach HUBBARD (1990). Da innerhalb von IFC-Gebäudemodellen Bauteile oft das Resultat mehrerer boolescher Operationen sind (z.B. um mehrere Fensteröffnungen von einer gegebenen Wand abzuziehen), wurde der Algorithmus von Hubbard angepasst, sodass mehrere boolesche Operationen gleichzeitig berechnet werden können. Durch diese Optimierung wird eine deutliche Reduzierung der benötigten Berechnungen und somit der Rechenzeit erreicht. KW - IFC KW - Boolesche Operationen KW - Visualisierung KW - Hubbard KW - Laidlaw Y1 - 2010 U6 - http://nbn-resolving.de/urn/resolver.pl?urn:nbn:de:gbv:wim2-20130107-18151 SN - 978-3-8322-9456-4 SP - 251 EP - 258 PB - Shaker Verlag CY - Aachen ER -